Peel House Progress – November 7, 2020

The rebar for the elevator footings are being delivered!
Placing the rebar getting ready to pour cement for the footings.
More demo being done upstairs.
Removing all the old wallpaper.
Electricians are working this week to run all the correct wiring.
Electricians in the attic!
Plumbers are also working this week on where the future pluming will go in the basement.
More kitchen demo. The blank area you see was filled in with concrete. They have no idea why it was done this way. Possibly sound proofing?

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Create a website or blog at WordPress.com

Up ↑

%d bloggers like this: