Concrete was poured this week!
More rebar was put in after the initial pour was dry.
The electricians have been hard at work!
Tons of electrical work done in the attic.
Wall in this room was removed. Soon this will be the handicap accessible bathrooms.
Lots of duct work being done in the basement.
Doors on the safe are finally gone!
Now this artwork on the safe will be on display for all to see!