Peel House Progress – December 26, 2020

Work on the elevator has started this week!
Another view of the soon the be elevator.
In the attic, they have completed the task of running electrical, so they are patching the walls back up.
Tests for the heating and cooling lines are being done to make sure they are functional after the install.
The pipes for the heating and cooling run from the basement up to the attic (previous photo).
On the second floor, more electrical is being run.